ARTICLE
18 August 2025

Adjudication Holds Firm: Eskom V Framatome And The Strength Of Contractual Dispute Resolution

KL
Herbert Smith Freehills Kramer LLP

Contributor

Herbert Smith Freehills Kramer is a world-leading global law firm, where our ambition is to help you achieve your goals. Exceptional client service and the pursuit of excellence are at our core. We invest in and care about our client relationships, which is why so many are longstanding. We enjoy breaking new ground, as we have for over 170 years. As a fully integrated transatlantic and transpacific firm, we are where you need us to be. Our footprint is extensive and committed across the world’s largest markets, key financial centres and major growth hubs. At our best tackling complexity and navigating change, we work alongside you on demanding litigation, exacting regulatory work and complex public and private market transactions. We are recognised as leading in these areas. We are immersed in the sectors and challenges that impact you. We are recognised as standing apart in energy, infrastructure and resources. And we’re focused on areas of growth that affect every business across the world.
The construction industry increasingly relies on adjudication as a fast and cost-effective way to resolve disputes under complex infrastructure contracts.
South Africa Litigation, Mediation & Arbitration

The construction industry increasingly relies on adjudication as a fast and cost-effective way to resolve disputes under complex infrastructure contracts. As this mechanism matures in South African practice, courts are often called upon to define its boundaries—especially when a disappointed party challenges the process or outcome. The recent decision of the Western Cape Division of the High Court in Eskom Holdings SOC Ltd v Framatome and Another provides a timely opportunity to examine how South African courts are enforcing adjudication and to reflect on its evolving role within the broader dispute-resolution landscape.

Background

The dispute arose from a major infrastructure project at Koeberg Nuclear Power Station—South Africa's only nuclear plant, which accounts for roughly 1,860 MW of generation capacity. Eskom entered into an NEC3 Engineering and Construction Contract with Areva NP for the replacement of six steam generators (three per reactor unit). Areva later ceded the contract to Framatome.

When Eskom postponed the planned works and instructed Framatome to stop, Framatome classified this as a compensation event under the NEC3 and submitted an associated cost claim. The Project Manager rejected the claim, prompting Framatome to refer the matter to adjudication as agreed under the contract.

The adjudicator issued two decisions. The first addressed the merits and found that Eskom's actions constituted a compensation event, entitling Framatome to additional time and money. The second determined the quantum payable. Eskom challenged both decisions, alleging that the adjudicator had exceeded his powers, failed to follow fair process, and had failed to provide adequate reasons. Framatome opposed the application and filed a counter-application seeking enforcement of the adjudicator's decisions and payment of the amounts awarded.

The Court's Findings

The Court dismissed Eskom's application and granted the relief sought by Framatome. The key aspects of the judgment include:

  1. Wide inquisitorial powers under clause W1.3(5).

    Clause W1.3(5) empowers an adjudicator to issue instructions to any "Party" (including the Project Manager) and to take "any other action" necessary to reach a decision. The court held that these powers are intentionally broad. Issuing instructions on quantum and directing the Project Manager to undertake a fresh assessment fell squarely within this mandate.
  2. No functus officio after the merits decision.

    The adjudicator remained seized of the dispute until the process set out in his merits decision, including the determination of quantum, was complete. Eskom's Notice of Dissatisfaction preserved its right to arbitration but did not terminate the adjudicator's mandate.
  3. Adjudication is contractual—not a common-law process.

    Adjudication under NEC3 is a creature of contract. Unless the parties expressly incorporate common-law requirements, the adjudicator need only follow the contractual procedure. The court went further noting that even if natural-justice principles applied, Eskom failed to participate meaningfully despite multiple invitations and therefore could not complain about unfairness.
  4. Adequate, reasoned quantum award.

    The 23-page quantum decision traced the contractual route to compensation, explained the use of agreed "benchmark rates," and detailed why the revised figures fairly reflected Framatome's entitlement. Eskom provided no counter-calculation despite having three opportunities to do so. The court found the reasons sufficient and described Eskom's criticism as contrived.
  5. Enforcement is immediate.

    Consistent with Supreme Court of Appeal authority, the court reaffirmed that adjudicators' decisions are binding and enforceable immediately, pending final determination by arbitration or litigation. Courts will interfere only in rare circumstances.

Implications

The judgment reinforces three practical lessons:

  1. Engage fully — A party that boycotts an adjudication risks an adverse, and immediately enforceable, decision.
  2. Respect the contract — NEC3's tight timelines and inquisitorial features are deliberate; courts will not rewrite them.
  3. Expect limited judicial intervention — Challenges based on errors of fact, law, or procedure seldom succeed unless they concern jurisdiction or breach an express contractual term.

A Broader Perspective

The decision aligns with a series of Supreme Court of Appeal judgments upholding contractual dispute mechanisms and underscores adjudication's role as a cash-flow tool. Its importance is highlighted by recent labour-force data: according to Stats SA's Quarterly Labour Force Survey, the construction sector added 176,000 jobs between Q2 and Q3 2025—the largest gain across all industries. As South Africa transforms into what government officials describe as "one vast construction site," robust adjudication processes remain vital for maintaining project momentum and protecting stakeholder interests.

Conclusion

Eskom v Framatome confirms that South African courts will enforce adjudication decisions swiftly and robustly, provided the adjudicator acts within the four corners of the contract. Parties tempted to "scrabble around" for reasons to avoid payment, without fully engaging in the process, do so at their peril.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.

Learn More